December 5, 2016 Minutes

River Hill Board of Directors

Meeting Minutes

December 5, 2016

 

 

 

Opening (Agenda 1):

Michael Cornell, called the Board meeting to order at 7:01 p.m. The following members were in attendance: Robert Choi, Harjeet Jandu, Richard Thomas, and Jason Zagnit. Susan Smith, Village Manager was in attendance. Board Members Mavourene Robinson and Liyan Zhang, Council Member Chao Wu, and Student Member Jennifer Zhang were absent. Mr. Zagnit left the meeting at 8:10 p.m. A list of attendees is on file with the Minutes.

 

Approval of the Agenda (Agenda 2):

Mr. Thomas made a motion to approve the agenda. Mr. Choi seconded the motion. The motion passed (5-0-0).

 

Administrative Items (Agenda 3):

Ms. Smith made a motion to approve the November 7, 2016 Minutes with an amendment to the minutes in Agenda Item 2 to state that both motions passed. Mr. Thomas seconded the motion. The motion passed (2-0-3).

 

Resident Speak out (Agenda 4):

None.

 

River Hill Square Development (River Hill Garden Center) (Agenda 5A):

The Board reviewed the letter to Steve Breeden that had previously been drafted (a copy is attached to the original minutes). It was the consensus of the Board to amend the letter to include the need to address the concerns raised by affected residents and the need for the state to address the traffic and safety issues along MD 108 between MD 32 and Trotter Road. Mr. Cornell will coordinate with Ms. Smith and Ms. Robinson to finalize the letter.

 

FY17 2nd Quarter Financials & Variance Analysis (Agenda 6A):

Ms. Smith presented the FY17 2nd quarter financial statements and variance analysis. Mr. Thomas made a motion to approve the financial statements and variance analysis as presented. Mr. Jandu seconded the motion. The motion passed (5-0-0).

 

Free Use Request (Agenda 6B):

Mr. Cornell made a motion to approve the use of Claret Hall by the River Hill High School cheerleading program on December 19 with the requirement that at a minimum they pay for the staffing and janitorial fees. Mr. Choi seconded the motion. The motion passed (4-0-0).

 

Executive Session (Agenda 7):

At 8:16 p.m., Mr. Cornell made a motion to move into Executive Session to discuss personnel matters. Mr. Thomas seconded the motion. The motion passed (4-0-0).

Mr. Choi made a motion to move out of Executive Session at 8:25 p.m. Mr. Thomas seconded the motion. The motion passed (4-0-0).

 

Manager’s Report (Agenda 8A):

A written report is on file with the original minutes.   Ms. Smith provided an update on the November 21, 2016 community meeting and the property damage and hate bias incidents occurring within the village.

 

Board Chair’s Report (Agenda 8B):

None.

 

Council Representative’s Report (Agenda 8C):

None.

 

Liaisons/Student Member (Agenda 8D):

None.

 

Board Speak Out (Agenda 9):

None.

 

Adjournment (Agenda 10):

Mr. Thomas made a motion to adjourn the meeting at 8:51 p.m. Mr. Choi seconded the motion. The motion passed (4-0-0).

 

Minutes submitted by: Susan M. Smith, Village Manager

 

Minutes Approved:   January 9, 2016

Garden Center Re-Development Moves Forward: Association Requests Consistency with Streetscape Plan and Design Guidelines

Security Development Corporation’s (SDC) Environmental Concept Plan (ECP-17-023) for the River Hill Square commercial development was submitted to the County’s Department of Planning and Zoning (DPZ) for review in November 2016. The ECP addresses stormwater management, sediment and erosion control, and grading and is very preliminary. The ECP must be approved prior to the submittal of the Site Development Plan that will contain more project detail. The project must also be reviewed by the County’s Design Advisory Panel. At this stage in the process, members of the community may submit written comments to the DPZ. Based on its initial review, DPZ has asked that a revised ECP be submitted

Simultaneously, the River Hill Community Association’s Board of Directors (RHCA) has asked SDC to redevelop the River Hill Garden Center property in a manner that is consistent with the Clarksville Pike Streetscape Plan and Design Guidelines adopted by the County (February 2016). It is the Boards’ opinion that while the need to address the cohesiveness of the corridor still exists, it is arguably greater now. This is due to the increase of commercial and residential development, lack of traffic re-design associated infrastructure improvements directly on the MD 108 corridor, and from development in the surrounding area.

It is the Association’s position that, in addition to any rights-of-way improvements required during re-development of this parcel, the State Highway Administration must address the ever-increasing congestion along MD 108 between MD 32 and Trotter Road. Comprehensive traffic analysis and solutions need to be developed and implemented that will ensure safety and address delay issues in the school zones, at Sheppard Lane, at the Linden Linthicum Lane intersection, and within the existing Clarksville commercial corridor. Further, it is the Board’s opinion that the necessity for a comprehensive traffic solution that is safe, scalable enough to acccomodate development that exceeds the originally approved usage and zoning application and will allow adherence to the approved Streetscape Plan should not be mitigated by any shortsighted, lower cost solutions that focus solely on the impact to the developer and the as yet unsecured commercial tenants.

The Board has asked the developer to make changes in response to the ongoing concerns of affected River Hill residents by establishing a berm and enhancing screening to mitigate the negative impact of lights and noise. The Board of Directors has also requested the design be amended to include:

•Buildings set within 25-feet of the curb to reinforce and improve upon the pedestrian character of the corridor;
•Primary building/retail entrances oriented toward the street;
and
•Pedestrian and bike accessibility enhancements.
It is the Board’s hope that the final design and development will be consistent with the Streetscape Plan and Design Guidelines and, as much as is possible, consider community input before the final selection of retailers. To ensure success, any future commercial development on the parcel must enhance the community in addition to providing establishments that are desired by residents.

Simpson Oaks Development Update

The Department of Planning and Zoning (DPZ) approved the Simpson Oaks residential development sketch plan (S-15-007) in December 2016. Tentative housing allocations have been granted for this subdivision (see table below).


PhaseNo.      Tentative Allocations      Allocation Year                 Preliminary Plan Submission

1                         129                                             2019                          Submitted within 9 months from sketch plan approval
                                                                                                                      (on or before September 17, 2017)


2                         55                                               2020                         Submitted between July 1 and December 31, 2017


The project has passed a preliminary assessment of the Adequate Public Facilities Ordinance test for roads, open school region, open elementary school district, and open middle school district.

The next step is for Chesapeake Realty Partners, the developer, to submit the Preliminary Plan for Phase 1. This plan will present the preliminary engineering to implement the approved sketch plan. The preliminary plan addresses the lot and road arrangement, traffic and noise conditions, forest conservation, environmental impact, sewage disposal, water supply, drainage, storm water management and proposed grading. During this stage, the County’s Subdivision Review Committee will review the plans. Once the preliminary plan is submitted, members of the community may contact DPZ with questions, provide written comments, and request a meeting with DPZ staff.

If the preliminary plans are not received by the milestone dates, the plan approval becomes null and void and the project will lose the tentative housing unit allocations. When this occurs, any plans resubmitted must be processed as a new sketch plan or preliminary equivalent sketch plan.

New Snow Plow Tracker for Howard County

In mid-December, Howard County Executive Allan H. Kittleman beta launched the County’s new cutting-edge snow plow tracker. Purchased from AT&T and BSM Technologies, the tracker replaces a system acquired more than 16 years ago.

“This new snow plow tracker is infinitely more advanced than the previous software,” said Kittleman. “Its real-time display will provide more accurate information for our residents during weather emergencies. It is also mobile friendly so it can be easily viewed on tablets and smart phones.”

Howard County has installed Automatic Vehicle Locators (AVLs) in 152 Department of Public Works (DPW) Bureau of High- way vehicles, including 135 pieces of snow removal equipment. The software downloads a digital snapshot from each AVL every 10 seconds, providing a comprehensive and constantly updated display of snow removal progress.

As an additional enhancement, Howard County has also purchased 25 “plug and play” AVLs that can be installed in contractor vehicles. That data will also be fed into the snow plow tracker when contractor vehicles are employed to present a more accurate picture of snow removal progress.

The sophisticated software will allow residents to monitor progress across four different time frames while snow removal is underway. Residents will be able to see if their streets have been treated in the last four hours, between four and eight hours ago, between eight and 12 hours ago, or more than 12 hours ago. The snow plow tracker will also aggregate highway traffic camera views, weather alerts and real-time traffic information into the display, providing residents with a one-stop shop for storm recovery information.

“Despite the significant commitment of DPW resources needed for the Ellicott City flood recovery, we worked on an aggressive timeline to get this up and running,” said Kittleman.

“By piggybacking onto an existing state contract, we were able to save on initial cost estimates and have the new system in place for this winter. Because this is a beta site, we have included a link for residents to submit comments and suggestions for future improvements.

The snow plow tracker is one component of a broader initiative to install AVLs in a fleet of 255 vehicles that will also include the Department of Inspections, Licensing and Permits, Bureau of Facilities and the Department of Recreation & Parks.

The County paid $32,400 to develop the mobile-friendly website. It will pay $12,000 annually in maintenance and support costs. The total cost of the AVL project, including the snow plow tracker, is $301,000.

The tracker can be accessed at HowardCountySnowTracker.org. A video tutorial on how to use the site can be found at https://youtu.be/ci3U__fncHA.